Q:
A) 101 men | B) 112 men |
C) 102 men | D) 120 men |
Answer: C) 102 men
Explanation:
Explanation:
From the above formula i.e (m1 x t1/w1) = (m2 x t2/w2)
so, [(34 x 8 x 9)/(2/5)] = [(M x 6 x 9)/(3/5)]
so, M = 136 men
Number of men to be added to finish the work = 136-34 = 102 men.