16
Q:

G is twice as fast as S in doing work. If G can do a work in 30 days less than S, how many days will they take to complete the work together?

A) 25 B) 20
C) 22 D) 15

Answer:   B) 20



Explanation:
Subject: Time and Work
Exam Prep: Bank Exams
Q:

X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part  of the total work?

 

A)  6 B) 4
C) 3 D) 12
 
Answer & Explanation Answer: B) 4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

7 1353
Q:

P can do a work in 10 days. Q can do the same work in 15 days. If they work together for 5 days, how much of the work will they complete?

A) 1/2 B) 2/3
C) 1/3 D) 5/6
 
Answer & Explanation Answer: D) 5/6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1406
Q:

P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?

 

A)  10 B)  12
C)  15 D) 18
 
Answer & Explanation Answer: B)  12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1055
Q:

S and T can finish a work in 50 days. They worked together for 20 days and then left. How much of the work is left?

A) 3/5 B) 1/3
C) 1/2 D) 2/5
 
Answer & Explanation Answer: A) 3/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1178
Q:

Type 1 workers are 2.5 times as efficient as type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 15 Type 2 workers to do the same work?

 

A) 13 B) 10
C) 12 D) 11
 
Answer & Explanation Answer: D) 11

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1302
Q:

P, Q and R alone can complete a work in 12, 15 and 20 days respectively. In how many days will they together complete the same work?

 

A) 4 B)  5  
C)  6   D) 3.5
 
Answer & Explanation Answer: D) 3.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 1136
Q:

A, B and C can complete the work in 4, 5 and 6 hours respectively. If they all work together and receive Rs. 777 as wages then find the share of A.

A) Rs. 300 B) Rs. 315
C) Rs. 326 D) Rs. 175
 
Answer & Explanation Answer: B) Rs. 315

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

8 948
Q:

S does half as much work as T in 1/7 of the time taken by T. If together they take 21 days to complete a work, then how may days shall S take to complete that work alone?

 

 

A) 26   B)  27  
C) 28   D) 32
 
Answer & Explanation Answer: B)  27  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 985