4
Q:
A) 4/3 days | B) 2 days |
C) 3/2 days | D) 4 days |
Answer: A) 4/3 days
Explanation:
Explanation:
Let the total number of documents to be printed be 12.
The number of documents printed by P in 1 day = 4.
The number of documents printed by Q in 1 day = 3.
The number of documents printed by R in 1 day = 2.
Thus, the total number of documents that can be printed by all the machines working simultaneously in a single day = 9.
Therefore, the number of days taken to complete the whole work = 12/9 = 4/3 days.