18
Q:
A) 64 | B) 62 |
C) 58 | D) 56 |
Answer: D) 56
Explanation:
Explanation:
Days remaining 124 – 64 = 60 days
Remaining work = 1 - 2/3 = 1/3
Let men required men for working remaining days be 'm'
So men required = (120 x 64)/2 = (m x 60)/1 => m = 64
Men discharge = 120 – 64 = 56 men.