A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?
A) 3 days
B) 26/3 days
C) 13/4 days
D) 24/5 days
Answer: D) 24/5 days
Explanation:
we know that m1 x d1 = m2 x d2 => 4 x 6 = 5 x d where d = no. of days taken by 5 men to paint d = 24/5 days.