A certain job was assigned to a group of women to do it in 20 days. But 12 women did not turn up for the job and the remaining did the job in 32 days. The original number of women in the group was?
A) 36
B) 32
C) 22
D) 28
Answer: B) 32
Explanation:
Let the total women in the group be 'W'
Then according to the given data,
W x 20 = (W-12) x 32
=> W = 32
Therefore, the total number of women in the group = 32