30
Q:
A) Total work | B) One-fourth work |
C) Half work | D) Two-third work |
Answer: C) Half work
Explanation:
Explanation:
A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.