A and B together finish a wor in 20 days.They worked together for 15 days and then B left. Afer another 10 days,A finished the remaining work. In how many days A alone can finish the job?
A) 30
B) 40
C) 50
D) 60
Answer: B) 40
Explanation:
(A+B)'s 15 days work =
Remaining work = 1/4
Now, 1/4 work is done by A in 10 days.
Whole work will be done by A in (10 x 4) = 40 days.
X can complete 5/7 part of a work in 10 days and Y can complete 3/4 part of the same work in 9 days. In how many days will both complete 13/21 part of the total work?
P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?
Type 1 workers are 2.5 times as efficient as type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 15 Type 2 workers to do the same work?