45
Q:
A) 4 days | B) 5 days |
C) 6 days | D) 7 days |
Answer: C) 6 days
Explanation:
Explanation:
Work donee by A and B in the first two hours, working alternatively = First hour A + Second hour B = (1/4) + (1/12) = 1/3.
Thus, the total time required to complete the work = 2 (3) = 6 days