89
Q:
A) 6 | B) 9 |
C) 5 | D) 7 |
Answer: D) 7
Explanation:
Explanation:
Let 1 woman's 1 day work = x.
Then, 1 man's 1 day work = x/2 and 1 child's 1 day work x/4.
So, (3x/2 + 4x + + 6x/4) = 1/7
28x/4 = 1/7 => x = 1/49
1 woman alone can complete the work in 49 days.
So, to complete the work in 7 days, number of women required = 49/7 = 7.