18
Q:
A) 2 days | B) 2.5 days |
C) 2.25 days | D) 3 days |
Answer: C) 2.25 days
Explanation:
Explanation:
1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3
Remaining work = 1 - 2/3 = 1/3
16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.
1/3 work is done by them in 27/4 x 1/3 = 9/4 days.