9
Q:

The following are lot sizing rules available for SAP R/3? 

Additional Details

A. Replenish to maximum stock level
B. Weekly lot size
C. Daily lot size
D. Fixed lot size
 

Answer:



Q:

To view the most up to date planning data (available stock, orders, reservations, etc) on a material,use the

A. Stock Requirement list.

B. Stock Overview report

C. List display of material and accounting documents

D. Standard Analysis for a material

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

21 6165
Q:

Subject to which prerequisites can a source of supply be assigned as early as during the MRP run?

A. The 'MRP-relevant' indicator must have been set in a contract item.

B. The source determination facility must be activated at the start of the MRP run.

C. A quota arrangement must exist and the quota arrangement usage indicator must allow use of the quota arrangement in materials planning.

D. An info record must exist for the relevant material and the vendor must have been flagged in the source list as the single/sole source of supply for the purposes of materials planning.

Answer

Answer : C , D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

4 3006
Q:

Which of the following master data can/must you use for pipeline meterials?

A. BOM(ascomponent)

B. Purchasing info record

C. Material master record

D. Vendor master record

E. Source list

Answer

Answer : A , B , C , D , E [all these]


 


Explanation:You must have created a material master record with a purchasing info record. To do this, you need a vendor master record. You can use the source list and BOM in connection with the pipeline material.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

4 3116
Q:

Which of the following MRP areas do not exist?

A. Consignment MRP area
B. Plant MRP area
C. Storage location MRP area
D. Subcontractor MRP area

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

5 4867
Q:

Which transaction shows the most up to date planning data?

A. Stock Requirement list

B. MRP list

C. Stock Overview report

D. List display of material and accounting documents

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

4 1906
Q:

What is the purpose of specifying a planning horizon?

A.  Only materials manifesting a planning-relevant change within the planning horizon are taken into account in the MRP run (where NETPL is used).
B.  To specify whether forecasts are included in the material requirement calculation.

C. To specify that only externally procured (and not internally procured) items are included in the net change MRP run.

D. To specify whether a NETCH (net change in complete horizon) or a NETPL (net change in planning horizon) will take place in the next MRP run.

Answer

Answer : A

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

3 2573
Q:

You enter a goods issue and receive the following message: "W: On , only 0.000 pieces are available". What do you conclude from this?

A. The message represents a warning which you can ignore by pressing the ENTER key.

B. The material exist in the specified storage location on the current day, however, it is unavailable, because of other reservations.

C. No stocks of the material exist anywhere in the entire plant.  Therefore, nothing can be withdrawn

D. Only the specified storage location does not contain any stocks of the material.  Therefore, nothing can be withdrawn.

Answer

Answer : A , B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

1 2733
Q:

How can you store long-term prices for services in the form of service conditions?

A. At the service and plant level

B. At the service and vendor level

C. At the service level

D. At the service, vendor and plant level

Answer

Answer: B , C , D


 


Explanation: Long term prices can be maintained at Service level, Service and Vendor level or Service, Vendor and Plant level.

Report Error

View answer Workspace Report Error Discuss

Subject: SAP MM

8 3135