A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution | B) Tolerances and thresholds help to define how often the risk management process will be performed |
C) Tolerances and thresholds determine what tools and data sources will be used in risk management | D) Tolerances and thresholds provide the basis for costing the risk management process as well as defining how risk activities will be recorded |
Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution
Explanation:
Explanation:
Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.