Q:
| A) To manage the effective and efficient use of resources. | B) To balance the portfolio among incremental and radical investments. |
| C) To maximize the value of the portfolio by careful examination of candidate projects and exclusion of those no meeting strategic objectives. | D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives. |
Answer: D) To ensure that the relationship between projects in the portfolio clearly reflects strategic objectives.
Explanation:
Explanation:
There is not necessarily a relationship between projects in a portfolio. Answer D is actually one of the goals of PROGRAM management. PMBOK Guide [1.4]