Q:
A) The WBS must be accurate and complete before this process can be used. | B) Since the cost is largely independent of the desired accuracy it is the methodology of choice. |
C) Its accuracy increases if the activities are smaller. | D) It is not a useful methodology in the early project planning phase. |
Answer: B) Since the cost is largely independent of the desired accuracy it is the methodology of choice.
Explanation:
Explanation:
“The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package.” PMBOK [7.1.2.4]