Q:
A) quality, resources, time | B) money, resources, quality |
C) scope, quality, planning | D) time, scope, cost |
Answer: D) time, scope, cost
Explanation:
Explanation:
Scope, quality, and cost are the triple constraints. Quality is a function of these three areas and can impact them; however it is not considered one of the components of the triple constraint. Therefore, Answer A, B, and C are incorect.