3
Q:
A) identify the risks which have the largest potential impact on the project. | B) determine which risks are most troubling to the customer. |
C) identify hidden requirements that were not recognized at the outset of the project. | D) determine which requirements will add the greatest customer satisfaction for the least effort. |
Answer: A) identify the risks which have the largest potential impact on the project.
Explanation:
Explanation:
“Sensitivity analysis helps to determine which risks have the most potential impact on the project.”