Q:
A) ensuring that the time, scope and cost baselines are consistent with an acceptable quality standard and with the customer’s expectations. | B) getting people working together effectively toward common project goals through appropriate training, management and leadership. |
C) effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization’s defined procedures. | D) ensuring that all the tools and techniques of the various planning processes are appropriately scaled to the complexity and risk exposure of the project. |
Answer: C) effectively integrating the processes among the project management process groups that are required to accomplish project objectives with an organization’s defined procedures.
Explanation:
Explanation:
Answers A, B and D all result from effectively integrating the work of the project management process groups. PMBOK [4.0]