Q:
A) 3 | B) 5 |
C) 6 | D) 9 |
Answer: B) 5
Explanation:
Explanation:
[(100 x 35) + (200 x 5)]men can finish the work in 1 day
Therefore, 4500 men can finish the work in 1 day. 100 men can finish it in 4500/100= 45 days.
This is 5 days behind Schedule