Q:
A) 24 days | B) 28 days |
C) 34 days | D) 35 days |
Answer: A) 24 days
Explanation:
Explanation:
Less Men, means more Days {Indirect Proportion}
Let the number of days be x then,
27 : 36 :: 18 : x
[Please pay attention, we have written 27 : 36 rather than 36 : 27, in indirect proportion, if you get it then chain rule is clear to you :)]
=>27x = 36 * 18
=> x = 24
So 24 days will be required to get work done by 27 men.