Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually?

A) 2:6:3 B) 2:3:6
C) 1:2:3 D) 3:1:2
 
Answer & Explanation Answer: A) 2:6:3

Explanation:

                                                A    :    B    :    C   

Ratio of efficiency               3     :    1    :    2   

Ratio of No.of days            1/3  :   1/1  :   1/2    

     or                                       2    :    6    :    3   

Hence A is correct.  

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

45 26776
Q:

A and B together can do a piece of work in 40 days. A having worked for 20 days, B finishes the remaining work alone in 60 days. In How many days shall B finish the  whole work alone?

A) 60 B) 70
C) 80 D) 90
 
Answer & Explanation Answer: C) 80

Explanation:

Let A's 1 day's work=x and B's 1 day's work=y

Then x+y = 1/40 and 20x+60y=1 

Solving these two equations , we get : x= 1/80 and y= 1/80

Therefore B's  1 day work = 1/80

Hence,B alone shall finish the whole work in 80 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

33 25911
Q:

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days  ?

A) 9 days B) 11 days
C) 13 days D) 15 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Ratio of times taken by A and B = 100 : 130 = 10 : 13.
Suppose B takes x days to do the work.

Then, 10 : 13 :: 23 : x     =>     x = ( 23 x 13/10 )     =>     x = 299 /10.

A's 1 day's work = 1/23 ;
B's 1 day's work = 10/299 .

(A + B)'s 1 day's work = ( 1/23 + 10/299 ) = 23/299 = 113 .

Therefore, A and B together can complete the work in 13 days. 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

52 25029
Q:

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days what is time taken by 15 men and 20 boys?

A) 4 days B) 6 days
C) 7 days D) 5 days
 
Answer & Explanation Answer: A) 4 days

Explanation:

Given that 

6 men and 8 boys can do a piece of work in 10 days 

26 men and 48 boys can do the same in 2 days

 

As the work done is equal,

10(6M + 8B) = 2(26M + 48B)

60M + 80B = 52M + 96B

=> M = 2B

=> B = M/2 ……(1)

 

Now Put (1) in 15M + 20B

=> 15M + 10M = 25M

Now, 6M + 8B in 10 days

=> (6M + 4M) 10 = 100M

Then D(25M) = 100M

=> D = 4 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

32 24666
Q:

A does half as much work as Band C does half as much work as A and B together. If C alone can finish the work in 40 days, then together ,all will finish the work in  ?

A) 17 + 4/7 days B) 13 + 1/3 days
C) 15 + 3/2 days D) 16 days
 
Answer & Explanation Answer: B) 13 + 1/3 days

Explanation:

C alone can finish the work in 40 days.
As given C does half as much work as A and B together
=> (A + B) can do it in 20 days
(A + B)s 1 days wok = 1/20.
A's 1 days work : B's 1 days Work = 1/2 : 1 = 1:2(given)
A's 1 day’s work = (1/20) x (1/3) = (1/60) [Divide 1/20 in the raio 1:2]
B's 1 days work = (1/20) x (2/3) = 1/30
(A+B+C)'s 1 day's work = (1/60) + (1/30) + (1/40) = 9/120 = 3/40

All the three together will finish it in 40/3 = 13 and 1/3 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Bank Clerk , Bank PO

46 23832
Q:

A is twice efficient as B and together they do the same work in as much time as C and D together. If C and D can complete the work in 20 and 30 daysrespectively, working alone ,then in how many days A can complete the work individually:

A) 12 days B) 18 days
C) 24 days D) 30 days
 
Answer & Explanation Answer: B) 18 days

Explanation:

                                              A     +      B        =      C     +     D 

                                              |              |                 |             | 

    Ratio of efficiency         10x   +    5x               9x     +   6x 

                                             |________|                 |_________|   

                                                   15x                           15x 

Therefore , ratio of efficiency of A:C  =10:9 

Therefore,  ratio of days taken by A:C = 9:10 

Therefore, number of days taken by A = 18 days                 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

54 23779
Q:

A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?

A) 50 B) 40
C) 45 D) 10
 
Answer & Explanation Answer: D) 10

Explanation:

Let the number of workers be x.

Now, Using work equivalence method,

X + (X-1) + (X-2)+ . . . . + 1 = X *55% of X

 

=> [X * (X+1)] / 2 = X * (55X/100)    [because, Series is in AP. Sum of AP = {No. of terms (first term+ last term)/2} ]

Therefore, X = 10 

 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

63 23425
Q:

9 men and 12 boys finish a job in 12 days, 12 men and 12 boys finish it in 10 days. 10 men and 10 boys shall finish it in how many days ?

A) 15 days B) 11 days
C) 14 days D) 12 days
 
Answer & Explanation Answer: D) 12 days

Explanation:

9M + 12B ----- 12 days ...........(1)
12M + 12B ------- 10 days........(2)
10M + 10B -------?
108M + 144B = 120M +120B
24B = 12M => 1M = 2B............(3)

From (1) & (3)

18B + 12B = 30B ---- 12 days

20B + 10B = 30B -----? => 12 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

22 22803