Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group?

A) 50 B) 40
C) 45 D) 10
 
Answer & Explanation Answer: D) 10

Explanation:

Let the number of workers be x.

Now, Using work equivalence method,

X + (X-1) + (X-2)+ . . . . + 1 = X *55% of X

 

=> [X * (X+1)] / 2 = X * (55X/100)    [because, Series is in AP. Sum of AP = {No. of terms (first term+ last term)/2} ]

Therefore, X = 10 

 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

63 23816
Q:

A can finish a work in 18 days and B can do the same work in half the time taken by A. then, working together, what part of the same work they can finish in a day ?

A) Total work B) One-fourth work
C) Half work D) Two-third work
 
Answer & Explanation Answer: C) Half work

Explanation:

A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

30 22041
Q:

A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 20 days and C alone in 60 days ,then B alone could do it in:

A) 20days B) 40 days
C) 50 days D) 60 days
 
Answer & Explanation Answer: D) 60 days

Explanation:

(A+B)'s 1 day's work=1/20 

C's 1 day work=1/60 

(A+B+C)'s 1 day's work= 1/20 + 1/60 = 1/15

 

Also A's 1 day's work =(B+C)'s 1 day's work 

Therefore,  we get: 2 x (A's 1 day 's work)=1/15 

=>A's 1 day's work=1/30 

 

Therefore, B's 1 day's work= 1/20 - 1/30 = 1/60

So, B alone could do the work in 60 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

88 21940
Q:

Rohit crosses a 700 metres wide road in 35 seconds. What is his speed (in km/hr)?

 

A) 54 B) 76
C) 72 D) 84
 
Answer & Explanation Answer: C) 72

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 21768
Q:

A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6 AM and they work alternately for one hour each. When will the work be completed?

A) 4 days B) 5 days
C) 6 days D) 7 days
 
Answer & Explanation Answer: C) 6 days

Explanation:

Work donee by A and B in the first two hours, working alternatively = First hour A + Second hour B = (1/4) + (1/12) = 1/3.

Thus, the total time required to complete the work  = 2 (3) = 6 days 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

45 21607
Q:

P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ?

A) 56 days B) 54 days
C) 60 days D) 64 days
 
Answer & Explanation Answer: D) 64 days

Explanation:

(P+Q)'s 1 day work = 1/24

P's 1 day work = 1/32

=> Q's 1 day work = 1/24 - 1/32 = 1/96

Work done by (P+Q) in 8 days = 8/24 = 1/3

Remainining work = 1 - 1/3 = 2/3

Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

22 19556
Q:

When A, B and C are deployed for a task , A and B together do 70% of the work and B and C together do 50% of the work. who is most efficient?

A) A B) B
C) C D) can't be determined
 
Answer & Explanation Answer: A) A

Explanation:

A + B= 70%   

B + C =50%   

  (A+B)+(B+C)-(A+B+C)= B

=> B= 20%     A= 50%        and   C=30%

Hence A is most efficient

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

31 19495
Q:

A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ?

A) 14 1/2 days B) 11 days
C) 13 1/4 days D) 12 6/7 days
 
Answer & Explanation Answer: D) 12 6/7 days

Explanation:

Let 'B' alone can do the work in 'x' days

6/30 + 18/x = 1

=> x = 22.5

 

1/30 + 1/22.5 = 7/90 

=> 90/7 = 12 6/7 days

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

29 19200